County of Forty Mile No. 8 - Hamlet of Burdett Sanitary System Upgrades 2015
Forty Mile No. 8 (County), Alberta
Federal contribution
$118,128
Federal share33%
of $360.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 31, 2015
20162017201820192020
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- County of Forty Mile No. 8
- Construction start
- Feb 29, 2016(actual)
- Construction end
- Jan 10, 2020(actual)
Against the original forecast
- Construction start6 months earlyforecast Sep 1, 2016
- Construction end4 months lateforecast Sep 1, 2019
Also in Forty Mile No. 8 (County)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46312 in the federal list. How to read these figures.