Back to projects

Drinking Water System and Sewer Expansion

Big Lakes, Alberta

completeWastewaterISF
Federal contribution
$636,814
Federal share18%

of $3.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 18, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jul 15, 2010

Also in Big Lakes

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28890 in the federal list. How to read these figures.