Cottonwood Road and Range Road 270 Road Resurfacing
Federal contribution
$848,000
Federal share33%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- County of Red Deer
- Construction start
- Jul 9, 2009(actual)
- Construction end
- Aug 25, 2009(actual)
Against the original forecast
- Construction start8 weeks earlyforecast Sep 1, 2009
- Construction end2 months earlyforecast Oct 31, 2009