53A Street Infrastructure Replacement
Federal contribution
$282,507
Federal share23%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Bonnyville
- Construction start
- Jul 28, 2010(actual)
- Construction end
- Oct 4, 2011(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jun 15, 2010
- Construction end4 weeks earlyforecast Oct 31, 2011
Also in Bonnyville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28991 in the federal list. How to read these figures.