Bridge Replacement on Spahats Forest Service Road

Clearwater, British Columbia

completeHighways and RoadsISF
Federal contribution
$47,500
Federal share48%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedApr 7, 2009
ApprovedJan 28, 2010
2010
Built

Approved 10 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Oct 1, 2010(actual)
Construction end
Nov 19, 2010(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Sep 5, 2010
  • Construction end3 weeks lateforecast Oct 30, 2010