Bridge Replacement on Spahats Forest Service Road
Federal contribution
$47,500
Federal share48%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedApr 7, 2009
ApprovedJan 28, 2010
2010
Built
Approved 10 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Oct 1, 2010(actual)
- Construction end
- Nov 19, 2010(actual)
Against the original forecast
- Construction start4 weeks lateforecast Sep 5, 2010
- Construction end3 weeks lateforecast Oct 30, 2010