Clearwater Septage Receiving Station Equalization Basin
Federal contribution
$139,998
Federal share50%
of $280.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 17, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Regional District of Thompson-Nicola
- Construction start
- Dec 18, 2017(actual)
- Construction end
- May 25, 2018(actual)
Against the original forecast
- Construction start7 weeks lateforecast Oct 31, 2017
- Construction end8 weeks lateforecast Mar 30, 2018
Also in Clearwater
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49780 in the federal list. How to read these figures.