Wastewater Treatment Upgrading
Federal contribution
$984,085
Federal share40%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 27, 2019
2020202120222023
Built
Approved 5 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- District of Clearwater
- Construction start
- Mar 14, 2020(actual)
- Construction end
- Jun 13, 2023(actual)
Against the original forecast
- Construction start5 months earlyforecast Aug 2, 2020
- Construction end7 months earlyforecast Dec 30, 2023
Also in Clearwater
- Clearwater - Active Transportation Network for Safe Connectivity$1.1M
- Water Supply Well No. 3 and Water Supply Main$1.1M
- Clearwater Septage Receiving Station Equalization Basin$140.0K
- Clearwater Sno-Drifters Trail Upgrade and Bridge Replacement$92.0K
- Bridge Replacement on Spahats Forest Service Road$47.5K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54026 in the federal list. How to read these figures.