Clearwater - Active Transportation Network for Safe Connectivity

Clearwater, British Columbia

completeActive TransportationCVRIS
Federal contribution
$1.1M
$1,079,780
Federal share80%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 15, 2021
20222023
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
District of Clearwater
Construction start
Jul 5, 2021(actual)
Construction end
Jul 20, 2023(actual)

Against the original forecast

  • Construction start9 months earlyforecast Apr 1, 2022
  • Construction end5 months earlyforecast Dec 31, 2023

Also in Clearwater

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60525 in the federal list. How to read these figures.