Centre Star Gulch Trail
Federal contribution
$10,212
Federal share25%
of $40.9K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 13, 2009
ApprovedAug 10, 2009
2010
Built
Approved 5 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Rossland
- Construction start
- Sep 1, 2009(actual)
- Construction end
- Jul 31, 2010(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 1, 2009
- Construction end4 months lateforecast Apr 15, 2010
Also in Rossland
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29363 in the federal list. How to read these figures.