South Sumas Road Sidewalk

Chilliwack, British Columbia

completeHighways and RoadsISF
Federal contribution
$13,751
Federal share25%

of $55.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedAug 10, 2009
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Chilliwack
Construction start
Jun 25, 2009(actual)
Construction end
Aug 31, 2009(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jun 1, 2009
  • Construction end7 months earlyforecast Mar 31, 2010