Whiting-Westview Bike Route

Coquitlam, British Columbia

completeActive TransportationISF
Federal contribution
$29,531
Federal share25%

of $118.1K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedAug 10, 2009
2010
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Coquitlam
Construction start
Dec 16, 2009(actual)
Construction end
Mar 1, 2010(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Nov 30, 2009
  • Construction end4 months earlyforecast Jun 30, 2010