Whiting-Westview Bike Route
Federal contribution
$29,531
Federal share25%
of $118.1K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 13, 2009
ApprovedAug 10, 2009
2010
Built
Approved 5 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Coquitlam
- Construction start
- Dec 16, 2009(actual)
- Construction end
- Mar 1, 2010(actual)
Against the original forecast
- Construction start2 weeks lateforecast Nov 30, 2009
- Construction end4 months earlyforecast Jun 30, 2010