Building a Community Trail - 100th Avenue
Fort St. John, British Columbia
Federal contribution
$247,431
Federal share25%
of $989.7K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 13, 2009
ApprovedAug 10, 2009
Built
Approved 5 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Fort St. John
- Construction start
- Aug 4, 2009(actual)
- Construction end
- Oct 30, 2009(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jul 1, 2009
- Construction end5 months earlyforecast Apr 15, 2010
Also in Fort St. John
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29599 in the federal list. How to read these figures.