Building a Community Trail - 100th Avenue

Fort St. John, British Columbia

completeActive TransportationISF
Federal contribution
$247,431
Federal share25%

of $989.7K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedAug 10, 2009
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Fort St. John
Construction start
Aug 4, 2009(actual)
Construction end
Oct 30, 2009(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jul 1, 2009
  • Construction end5 months earlyforecast Apr 15, 2010

Also in Fort St. John

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29599 in the federal list. How to read these figures.