Schedule

AnnouncedSep 11, 2009
ApprovedJan 26, 2010
20102011
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Altona
Construction start
May 25, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start3 weeks lateforecast May 1, 2010
  • Construction end3 months lateforecast Jul 30, 2011