Upgrade of Lift Station and Sewer Relining
Federal contribution
$469,966
Federal share32%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 2, 2019
20202021
Built
Approved 5 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Altona
- Construction start
- Jun 14, 2021(actual)
- Construction end
- Oct 1, 2021(actual)
Against the original forecast
- Construction start14 months lateforecast Apr 1, 2020
- Construction end2 months earlyforecast Nov 30, 2021