Altona Lagoon Upgrade Phase 2 - Organic Treatment Capacity

Altona, Manitoba

completeWastewaterSCF
Federal contribution
$1.3M
$1,273,976
Federal share33%

of $3.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 31, 2015
2016
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Altona
Construction start
May 1, 2016(actual)
Construction end
Dec 6, 2016(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast May 15, 2016
  • Construction end5 weeks lateforecast Oct 31, 2016

Also in Altona

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46330 in the federal list. How to read these figures.