Lagoon Expansion - Phase 3, Altona

Altona, Manitoba

completeWastewaterCWWF
Federal contribution
$2.3M
$2,250,000
Federal share50%

of $4.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 25, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Altona
Construction start
Apr 10, 2017(actual)
Construction end
Mar 30, 2018(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast May 1, 2017
  • Construction end4 months lateforecast Dec 1, 2017

Also in Altona

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47118 in the federal list. How to read these figures.