Liumchen Creek Forest Service Road

Chilliwack, British Columbia

completeHighways and RoadsISF
Federal contribution
$157,500
Federal share50%

of $315.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedApr 7, 2009
ApprovedJan 28, 2010
2010
Built

Approved 10 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jul 6, 2010(actual)
Construction end
Oct 30, 2010(actual)

Against the original forecast

  • Construction end5 months earlyforecast Mar 31, 2011

Also in Chilliwack

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29939 in the federal list. How to read these figures.