Vankleek Hill Arena Elevator Replacement

Champlain, Ontario

completeSportISF
Federal contribution
$66,667
Federal share33%

of $200.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Champlain
Construction start
Apr 12, 2010(actual)
Construction end
Jul 21, 2010(actual)

Against the original forecast

  • Construction start4 months lateforecast Dec 1, 2009
  • Construction end3 months earlyforecast Oct 30, 2010