Reconstruction of 4 Kilometres of 8th Concession - Ramsay

Mississippi Mills, Ontario

completeHighways and RoadsISF
Federal contribution
$158,714
Federal share33%

of $480.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Mississippi Mills
Construction start
Aug 10, 2009(actual)
Construction end
Oct 15, 2009(actual)

Against the original forecast

  • Construction start9 months earlyforecast May 15, 2010
  • Construction end9 months earlyforecast Jul 31, 2010

Also in Mississippi Mills

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29983 in the federal list. How to read these figures.