Spring Street Reconstruction, and Water and Sewer Main Replacement
Federal contribution
$147,000
Federal share33%
of $441.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Mississippi Mills
- Construction start
- May 17, 2010(actual)
- Construction end
- Nov 3, 2010(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Jun 1, 2010
- Construction end5 weeks lateforecast Sep 30, 2010
Also in Mississippi Mills
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29987 in the federal list. How to read these figures.