Replacement of the Levi Bridge

Mississippi Mills, Ontario

completeHighways and RoadsRNIS
Federal contribution
$423,499
Federal share50%

of $847.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 2, 2020
2021
Built

Approved 2 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Mississippi Mills
Construction start
Jun 1, 2021(actual)
Construction end
Oct 28, 2021(actual)

Against the original forecast

  • Construction end4 months earlyforecast Feb 25, 2022

Also in Mississippi Mills

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54594 in the federal list. How to read these figures.