Union Street Watermain Rehabilitation and Extension

Mississippi Mills, Ontario

completeDrinking WaterGIS
Federal contribution
$850,650
Federal share40%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2022
202320242025
Built

Approved 6 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Mississippi Mills
Construction start
May 15, 2024(actual)
Construction end
Jul 18, 2025(actual)

Against the original forecast

  • Construction end3 weeks lateforecast Jun 27, 2025