Dundas Street Gateway

London, Ontario

completeHighways and RoadsISF
Federal contribution
$1.0M
$1,000,000
Federal share33%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of London
Construction start
May 17, 2010(actual)
Construction end
Dec 31, 2010(actual)

Against the original forecast

  • Construction start2 weeks lateforecast May 1, 2010
  • Construction end4 weeks lateforecast Nov 30, 2010