Dundas Street Gateway
Federal contribution
$1.0M
$1,000,000
Federal share33%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of London
- Construction start
- May 17, 2010(actual)
- Construction end
- Dec 31, 2010(actual)
Against the original forecast
- Construction start2 weeks lateforecast May 1, 2010
- Construction end4 weeks lateforecast Nov 30, 2010