Highbury Bridge Rehabilitation
Federal contribution
$506,371
Federal share32%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built
Approved 22 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of London
- Construction start
- May 10, 2010(actual)
- Construction end
- Mar 24, 2011(actual)
Against the original forecast
- Construction start4 weeks lateforecast Apr 15, 2010