Back to projects

Repairs to Sewer System - Old North/Downtown

London, Ontario

completeWastewaterISF
Federal contribution
$866,614
Federal share33%

of $2.6M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of London
Construction start
May 3, 2010(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start10 months lateforecast Jul 1, 2009

Also in London

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30362 in the federal list. How to read these figures.