Municipal Office Addition
Macdonald, Meredith and Aberdeen Additional, Ontario
Federal contribution
$30,414
Federal share31%
of $99.3K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Macdonald, Meredith and Aberdeen Additional, Township of
- Construction start
- Jul 8, 2009(actual)
- Construction end
- Dec 15, 2009(actual)
Against the original forecast
- Construction start8 weeks lateforecast May 15, 2009
Also in Macdonald, Meredith and Aberdeen Additional
- Rehabilitation of Hurley Park Tennis Courts$79.7K
- Rehabilitation of Drinking Water Supply and Treatment System Component$54.7K
- Rehabilitation of sanitary sewage system components including the Supervisory Control and Data Acquisition system (SCADA) and controls at two sewage lift stations, sewage pumps and valves.$47.4K
- Sportsplex Upgrades$38.5K
- Milligan Gazebo$18.8K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30395 in the federal list. How to read these figures.