Rehabilitation of Hurley Park Tennis Courts

Macdonald, Meredith and Aberdeen Additional, Ontario

completeActive TransportationCVRIS
Federal contribution
$79,709
Federal share80%

of $99.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 7, 2021
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jul 1, 2021(actual)
Construction end
Aug 16, 2021(actual)