Sportsplex Upgrades

Macdonald, Meredith and Aberdeen Additional, Ontario

completeSportISF
Federal contribution
$38,450
Federal share31%

of $125.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jul 13, 2009(actual)
Construction end
Nov 25, 2009(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jun 1, 2009
  • Construction end5 weeks earlyforecast Dec 31, 2009