Rehabilitation of sanitary sewage system components including the Supervisory Control and Data Acquisition system (SCADA) and controls at two sewage lift stations, sewage pumps and valves.

Macdonald, Meredith and Aberdeen Additional, Ontario

completeWastewaterCWWF
Federal contribution
$47,438
Federal share50%

of $94.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
201820192020
Built
Program
Clean Water and Wastewater Fund
Construction start
Nov 1, 2017(actual)
Construction end
Dec 31, 2019(actual)

Against the original forecast

  • Construction start10 months lateforecast Jan 1, 2017
  • Construction end2 months lateforecast Oct 31, 2019