Rehabilitation of Ardoch Road
Federal contribution
$250,000
Federal share33%
of $750.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of North Frontenac
- Construction start
- Dec 10, 2009(actual)
- Construction end
- Oct 25, 2010(actual)
Against the original forecast
- Construction end6 weeks lateforecast Sep 15, 2010
Also in North Frontenac
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30439 in the federal list. How to read these figures.