Back to projects

Renovation and Remediation North Frontenac Twp.

North Frontenac, Ontario

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 15, 2021
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Township of North Frontenac
Construction start
Sep 14, 2021(actual)
Construction end
Dec 10, 2021(actual)

Against the original forecast

  • Construction end3 weeks earlyforecast Dec 31, 2021

Also in North Frontenac