Lac des Milles Lacs Green Energy

North Frontenac, Ontario

completeGreen EnergySCF
Federal contribution
$260,662
Federal share33%

of $782.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 18, 2016
2017
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Jun 1, 2017(actual)
Construction end
Oct 31, 2017(actual)

Against the original forecast

  • Construction end3 months lateforecast Jul 31, 2017

Also in North Frontenac

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46394 in the federal list. How to read these figures.