Reconstruction of Myers Cave Road and Harlowe Road
Federal contribution
$887,865
Federal share60%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 22, 2019
20202021
Built
Approved 4 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Municipality of Frontenac
- Construction start
- Jul 20, 2020(actual)
- Construction end
- Aug 9, 2021(actual)
Against the original forecast
- Construction end3 weeks earlyforecast Aug 31, 2021
Also in North Frontenac
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54221 in the federal list. How to read these figures.