Argyle Arena Lighting Upgrade

London, Ontario

completeGreen EnergyISF
Federal contribution
$29,916
Federal share30%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of London
Construction start
Sep 1, 2009(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start7 months earlyforecast Apr 1, 2010