Book Road Reconstruction
Federal contribution
$63,332
Federal share26%
of $240.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Grimsby
- Construction start
- Aug 24, 2009(actual)
- Construction end
- Oct 13, 2010(actual)
Against the original forecast
- Construction start2 weeks lateforecast Aug 9, 2009
Also in Grimsby
- Baker Road Wastewater Treatment Plant Upgrade$8.3M
- West Niagara YMCA$5.3M
- Grimsby Town Hall Redevelopment/Renovation$2.2M
- Replacement of Main Street and Elm Street Watermains$1.1M
- Water Main Rehabilitation 2021 - Upgrading of Cast Iron Water to PVC including Isolation Valves, Hydrants, and Service Connections$938.5K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30461 in the federal list. How to read these figures.