Roof Replacement - Farquharson Arena
Federal contribution
$191,804
Federal share31%
of $620.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built
Approved 22 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of London
- Construction start
- Oct 1, 2009(actual)
- Construction end
- Jan 31, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Aug 1, 2009
- Construction end8 weeks earlyforecast Mar 31, 2011
Also in London
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30466 in the federal list. How to read these figures.