Replacing the Roof and Compressors at Carling Arena

London, Ontario

completeSportISF
Federal contribution
$206,666
Federal share33%

of $620.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built

Approved 22 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of London
Construction start
Oct 1, 2009(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Sep 1, 2009

Also in London

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30476 in the federal list. How to read these figures.