Replacing the Roof and Compressors at Carling Arena
Federal contribution
$206,666
Federal share33%
of $620.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built
Approved 22 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of London
- Construction start
- Oct 1, 2009(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start4 weeks lateforecast Sep 1, 2009