Improvements to City Hall

London, Ontario

completeAdministration, Emergency and Public WorksISF
Federal contribution
$1.6M
$1,566,667
Federal share33%

of $4.7M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of London
Construction start
May 17, 2010(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Apr 30, 2010