Improvements to City Hall
Federal contribution
$1.6M
$1,566,667
Federal share33%
of $4.7M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of London
- Construction start
- May 17, 2010(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start2 weeks lateforecast Apr 30, 2010
Also in London
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30505 in the federal list. How to read these figures.