Back to projects

St. Andrew Street Reconstruction

West Perth, Ontario

completeHighways and RoadsISF
Federal contribution
$404,000
Federal share33%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built

Approved 22 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Municipality of West Perth
Construction start
Aug 17, 2009(actual)
Construction end
May 21, 2010(actual)

Against the original forecast

  • Construction end5 months earlyforecast Oct 29, 2010

Also in West Perth

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30521 in the federal list. How to read these figures.