Water Bottle Filling Stations; Heating, Ventilation and Air Conditioning (HVAC) Installation - Cooling

West Perth, Ontario

completeVentilationCVRIS
Federal contribution
$912,000
Federal share80%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2021
20222023
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 30, 2021(actual)
Construction end
Apr 30, 2023(actual)

Against the original forecast

  • Construction start4 months lateforecast Feb 19, 2021
  • Construction end8 months earlyforecast Dec 31, 2023

Also in West Perth

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58677 in the federal list. How to read these figures.