Henry Street Reconstruction
Federal contribution
$382,117
Federal share50%
of $764.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 19, 2019
2020
Built
Approved 4 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Municipality of West Perth
- Construction start
- Sep 1, 2019(actual)
- Construction end
- Jun 9, 2020(actual)
Against the original forecast
- Construction start6 weeks earlyforecast Oct 14, 2019
- Construction end5 months earlyforecast Oct 30, 2020
Also in West Perth
- Water Bottle Filling Stations; Heating, Ventilation and Air Conditioning (HVAC) Installation - Cooling$912.0K
- Keterson Park Multi-Use Community Facility$461.1K
- HVAC Upgrades; Window Replacements$438.9K
- St. Andrew Street Reconstruction$404.0K
- Mitchell Drinking Water Treatment/Distribution Center Improvements$209.7K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54227 in the federal list. How to read these figures.