Keterson Park Multi-Use Community Facility
Federal contribution
$461,130
Federal share37%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
20222023
Built
Approved 5 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Municipality of West Perth
- Construction start
- Nov 1, 2022(actual)
- Construction end
- Oct 26, 2023(actual)
Against the original forecast
- Construction start4 weeks lateforecast Oct 3, 2022
- Construction end5 months lateforecast May 31, 2023
Also in West Perth
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57712 in the federal list. How to read these figures.