Keterson Park Multi-Use Community Facility

West Perth, Ontario

completeRecreationCCRIS
Federal contribution
$461,130
Federal share37%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
20222023
Built

Approved 5 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Municipality of West Perth
Construction start
Nov 1, 2022(actual)
Construction end
Oct 26, 2023(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Oct 3, 2022
  • Construction end5 months lateforecast May 31, 2023