Calton Line Rehabilitation

Bayham, Ontario

completeHighways and RoadsISF
Federal contribution
$568,054
Federal share28%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
County of Elgin
Construction start
Oct 1, 2009(actual)
Construction end
May 18, 2010(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Sep 15, 2009
  • Construction end3 months earlyforecast Aug 27, 2010