Calton Line Rehabilitation
Federal contribution
$568,054
Federal share28%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- County of Elgin
- Construction start
- Oct 1, 2009(actual)
- Construction end
- May 18, 2010(actual)
Against the original forecast
- Construction start2 weeks lateforecast Sep 15, 2009
- Construction end3 months earlyforecast Aug 27, 2010
Also in Bayham
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30573 in the federal list. How to read these figures.