Port Burwell - Robinson St-Beach Storm Sewer Replacement - Optimization

Bayham, Ontario

completeWastewaterCWWF
Federal contribution
$156,076
Federal share41%

of $379.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of Bayham
Construction start
Feb 1, 2017(actual)
Construction end
Dec 22, 2017(actual)