Back to projects

Vienna Community Sidewalk Construction

Bayham, Ontario

completeActive TransportationCVRIS
Federal contribution
$85,758
Federal share80%

of $107.2K total eligible cost; the rest comes from other partners.

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Municipality of Bayham
Construction start
May 3, 2021(actual)
Construction end
May 30, 2021(actual)

Against the original forecast

  • Construction end4 weeks earlyforecast Jun 30, 2021

Also in Bayham

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59586 in the federal list. How to read these figures.