Back to projects

Straffordville Community Hub Construction & Rehabilitation

Bayham, Ontario

underwayRecreationCCRIS
Federal contribution
$801,320
Federal share40%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 11, 2021
today
2021202320252027
BuiltForecast

Approved 5 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Municipality of Bayham
Construction start
Nov 30, 2025(actual)
Construction end
Dec 31, 2026(forecast)

Also in Bayham

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57638 in the federal list. How to read these figures.