Ed Blake Park - New Park Features
Federal contribution
$391,666
Federal share33%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of London
- Construction start
- Oct 1, 2009(actual)
- Construction end
- Sep 30, 2011(actual)
Against the original forecast
- Construction start6 months earlyforecast Apr 1, 2010
- Construction end3 months lateforecast Jun 30, 2011
Also in London
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30630 in the federal list. How to read these figures.