Medway Park - Improve Park Amenities
Federal contribution
$316,666
Federal share33%
of $950.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of London
- Construction start
- Mar 22, 2010(actual)
- Construction end
- Oct 30, 2010(actual)
Against the original forecast
- Construction start3 months lateforecast Jan 1, 2010
- Construction end4 weeks lateforecast Sep 30, 2010
Also in London
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30644 in the federal list. How to read these figures.