Fairgrounds Road Upgrade
Federal contribution
$200,000
Federal share33%
of $600.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Severn
- Construction start
- Jul 13, 2009(actual)
- Construction end
- Sep 9, 2009(actual)
Against the original forecast
- Construction end3 months earlyforecast Dec 15, 2009
Also in Severn