Replacement of Sewer Main on Brick Pond Road

Severn, Ontario

completeWastewaterCWWF
Federal contribution
$180,557
Federal share32%

of $571.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 16, 2017
20182019
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of Severn
Construction start
May 1, 2017(actual)
Construction end
Mar 31, 2019(actual)

Against the original forecast

  • Construction end3 months lateforecast Dec 31, 2018

Also in Severn

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48437 in the federal list. How to read these figures.